Cleaning sits at the end of the development programme, which is where delays cost the most. Planning it as phases rather than as one final scramble is what protects the handover date.

Phase one: builders' clean

Once trades are out, bulk dust, packaging, offcuts and debris come out first. This phase is about volume, not finish, and it determines how efficient the detailed clean can be.

Phase two: detailed post-construction cleaning

Surfaces, fittings, frames, glass, tracks and floors are worked through in sequence. Residue — paint spots, adhesive, cement film — is handled where it can be removed safely, and reported where it cannot.

Phase three: pre-handover clean

The final pass happens as close to inspection or occupation as access allows, because a cleaned building that sits open for two weeks is not a cleaned building.

Common area handover

Common areas hand over to the body corporate or estate management. A first clean at handover, rolling into a recurring common-area contract, avoids the gap where nobody is responsible yet.

What to confirm before committing to a date

Cleaning crews need the same things trades do, and they are usually the last to get them.

  • Access, keys and security arrangements
  • Power and water availability on site
  • Whether trades are genuinely finished in that section
  • Who removes structural rubble, and by when
  • How many units or areas release at a time